Play Live Radio
Next Up:
0:00
0:00
0:00 0:00
Available On Air Stations
Make a sustaining gift today to support local journalism!
What Is Northern Pass? Northern Pass is a proposal to run 192 miles of new power lines from Canada, through northern New Hampshire, south to Concord, and then eastward to Deerfield. The project is a collaboration between Eversource (previously known as Public Service of New Hampshire) and Hydro-Quebec, which is owned by the provincial government of Quebec. The utilities say the $1.6 billion Northern Pass project would transport 1,090 megawatts of electricity from Quebec – which derives more than 90 percent of its power from hydroelectric dams – to the New England power grid.The ControversyNorthern Pass has proved an incredibly controversial issue in New Hampshire, especially in the North CountryThe project has generated considerable controversy from the beginning. Despite its statewide impacts, many of the projects most dedicated opponents come from the sparsely-populated and heavily forested North Country.Eversource says the new lines would bring jobs and tax revenue to this struggling part of the state. But opponents of the project say it would mean only temporary jobs for residents when it's under construction. They also say it will deface New Hampshire's forestland, hurting tourism and lowering property values. Depending on the location, developers say the project's towers will range from 85 to 135 feet tall.Polls have consistently found the public remains sharply divided on this issue.Some critics have pushed for the entire project to be buried. Politicians ranging from Sen. Maggie Hassan to former Sen. Kelly Ayotte to 2012 GOP presidential candidate Newt Gingrich have floated this move as having the potential to soften opposition. Eversource maintains this would be too expensive, and would effectively make the project impossible to pursue. The Route: Real Estate Chess Plays Out In The North Country Northern Pass and its opponents have been fighting over control of land along potential routesNorthern Pass has considered a number of routes for the project, but has publicly announced three. The first, unveiled in 2011, faced major backlash from North Country residents and environmental groups. Over the next couple of years, the project and its primary opponent the Society for the Protection of New Hampshire Forests played a prolonged chess match over parcels of North Country land. Northern Pass ultimately spent more than $40 million purchasing acres of undeveloped land in the North Country. Meanwhile, the Forest Society undertook an aggressive fundraising campaign and sought a slew of conservation easements to block potential routes.This maneuvering narrowed the options for Northern Pass. One lingering possibility was exercising eminent domain. Northern Pass publicly stated it was not interested in pursuing eminent domain. But in 2012, in response to strong statewide opposition, the Legislature closed the option altogether, outlawing the practice except in cases where a new transmission line was needed to maintain the reliability of the electric system.By the spring of 2013, Northern Pass opponents believed the project was essentially "cornered" into trying to route the power line through a large conservation easement, called the Connecticut Lakes Headwaters. The governor at that time, Democrat Maggie Hassan, said she opposed such a move on the part of Northern Pass.Second Time Around: Northern Pass Announces Alternative RouteIn June of 2013, Northern Pass unveiled its second proposed route. Abandoning its previous strategy (and $40 million in land purchases) altogether, the project proposed building along existing state and local North Country roadways in Clarksville and Stewartstown. In a nod to project opponents, Northern Pass also said it will bury 7.5 miles of line in Stewartstown, Clarksville, and under the Connecticut River. That raised the price tag on the project from $1.2 billion as initially proposed to about $1.4 billion. While opponents said this move was progress, many – including the Forest Society – maintained that Northern Pass should be able to bury all 180 miles of power lines.Final Route: Burial through the White Mountains0000017a-15d9-d736-a57f-17ff8a620000 After years of continued opposition, Northern Pass made its final concession to critics. It downsized the powerline from an initial proposal of 1,200 megawatts to 1,090 to take advantage of a new technology, known as HVDC lite. This move made it more economical to bury portions of the line, and Eversource said it was now willing to bury 52 additional miles of the project. The new route would be alongside state roadways as the project passed through the White Mountain National Forest.While the governor called the change “an important improvement,” she also said “further improvements” to the project should be made. The partial burial did not placate the project’s fiercest opponents, but some speculated that it would help the project clear one significant hurdle: whether it would get approval to use public lands from the top official at the White Mountain National Forest. The move pushed the estimated price tag up again, to $1.6 billion, now for a project that would deliver less power.With its new route in hand, project officials filed to build the project in October of 2015.Before the Site Evaluation CommitteeThe application to state officials was likely the longest and most complicated in the state’s history, and 161 individuals, interest groups, and municipalities asked to be allowed to participate in the process to evaluate the merits of the project.Given the size and complexity of the project, many of the interveners pushed for a longer review than the standard one year that state law dictates. In May of 2016, those groups got their wish, and the decision was pushed back 9 months. The final deadline was set for September of 2017. However, once the proceeding got under way, it was clear that even this delay would not allow time to hear from all of the witnesses called by the various interveners. Early in September of 2017 it was delayed again, with a final decision set for February 2018.DeniedOn February 1st, 2018, the New Hampshire Site Evaluation Committee voted unanimously to deny the permit for Northern Pass, a decision that triggered an appeals process that was taken up by the New Hampshire Supreme Court in late 2018.In May of 2019, the court heard orgal arguments on the appeal.On July 19, 2019, the court issued its ruling. In a unanimous decision, the SEC's rejection of the project was upheld, likely marking the end of Northern Pass as it was proposed.

N.H. Supreme Court Says Eversource Can Invest In Gas Pipelines For Electric Supply

Consumer Energy
/
Flicker CC

The New Hampshire Supreme Court says electric utilities like Eversource should be allowed to invest in natural gas pipelines.

Tuesday’s ruling reverses a 2016 order by the state Public Utilities Commission.

Eversource wanted to invest in a natural gas pipeline called Access Northeast, they said, as a means of shoring up the region's electric fuel supplies.

Regulators said that would go against the legislature's restructuring of New Hampshire's electric system.

That policy, also known as deregulation, says companies can't own both power plants and the means of delivering that power to customers.

Now, the state Supreme Court has ruled Eversource should be able to invest in pipeline capacity.

“We discern that the primary intent of the legislature in enacting [restructuring] was to reduce electricity costs to consumers,” the majority opinion states.

The court declined to address whether natural gas supply counts as electric generation, but says that more broadly, restructuring was meant to lower rates, not just separate generation from transmission.

One justice dissented, saying in a minority opinion that “the majority misses the forest for the trees.”

And state ratepayer advocate Don Kreis, who works alongside the PUC, casts the ruling as a threat to restructuring in a Tweet

Meanwhile, Eversource is lauding the ruling, saying in a statement it has “broad implications for New Hampshire’s energy future.”

“For example, there is little question that customers in New Hampshire and the region will benefit from an increased supply of natural gas to be used to create electricity,” the statement says.

The company says it will also ask the PUC to reconsider its denial of a power purchase agreement with Hydro Quebec over the besieged Northern Pass transmission line.

“The PUC’s denial, which led to removal of the agreement and its associated benefits from the New Hampshire siting application, was based on the same flawed legal analysis that the Supreme Court today overturned,” Eversource says.

The PUC will now have to reconsider Eversource's natural gas case with the court's ruling in mind.

Meanwhile, the state Site Evaluation Committee – which has some overlap with the PUC – will meet Thursday to discuss whether to re-hear the Northern Pass application, which it rejected earlier this year.

The International Brotherhood of Electrical Workers, which would get to help build projects like Northern Pass, also praised the Supreme Court decision Tuesday.

They’re calling for PUC and SEC chair Martin Honigberg to resign, and for the SEC to reconsider Northern Pass with the new legal analysis of the restructuring law in mind.

Annie has covered the environment, energy, climate change and the Seacoast region for NHPR since 2017. She leads the newsroom's climate reporting project, By Degrees.
Related Content

You make NHPR possible.

NHPR is nonprofit and independent. We rely on readers like you to support the local, national, and international coverage on this website. Your support makes this news available to everyone.

Give today. A monthly donation of $5 makes a real difference.