Play Live Radio
Next Up:
0:00
0:00
0:00 0:00
Available On Air Stations
Donate your vehicle during the month of April or May and you'll be entered into a $500 Visa gift card drawing!
What Is Northern Pass? Northern Pass is a proposal to run 192 miles of new power lines from Canada, through northern New Hampshire, south to Concord, and then eastward to Deerfield. The project is a collaboration between Eversource (previously known as Public Service of New Hampshire) and Hydro-Quebec, which is owned by the provincial government of Quebec. The utilities say the $1.6 billion Northern Pass project would transport 1,090 megawatts of electricity from Quebec – which derives more than 90 percent of its power from hydroelectric dams – to the New England power grid.The ControversyNorthern Pass has proved an incredibly controversial issue in New Hampshire, especially in the North CountryThe project has generated considerable controversy from the beginning. Despite its statewide impacts, many of the projects most dedicated opponents come from the sparsely-populated and heavily forested North Country.Eversource says the new lines would bring jobs and tax revenue to this struggling part of the state. But opponents of the project say it would mean only temporary jobs for residents when it's under construction. They also say it will deface New Hampshire's forestland, hurting tourism and lowering property values. Depending on the location, developers say the project's towers will range from 85 to 135 feet tall.Polls have consistently found the public remains sharply divided on this issue.Some critics have pushed for the entire project to be buried. Politicians ranging from Sen. Maggie Hassan to former Sen. Kelly Ayotte to 2012 GOP presidential candidate Newt Gingrich have floated this move as having the potential to soften opposition. Eversource maintains this would be too expensive, and would effectively make the project impossible to pursue. The Route: Real Estate Chess Plays Out In The North Country Northern Pass and its opponents have been fighting over control of land along potential routesNorthern Pass has considered a number of routes for the project, but has publicly announced three. The first, unveiled in 2011, faced major backlash from North Country residents and environmental groups. Over the next couple of years, the project and its primary opponent the Society for the Protection of New Hampshire Forests played a prolonged chess match over parcels of North Country land. Northern Pass ultimately spent more than $40 million purchasing acres of undeveloped land in the North Country. Meanwhile, the Forest Society undertook an aggressive fundraising campaign and sought a slew of conservation easements to block potential routes.This maneuvering narrowed the options for Northern Pass. One lingering possibility was exercising eminent domain. Northern Pass publicly stated it was not interested in pursuing eminent domain. But in 2012, in response to strong statewide opposition, the Legislature closed the option altogether, outlawing the practice except in cases where a new transmission line was needed to maintain the reliability of the electric system.By the spring of 2013, Northern Pass opponents believed the project was essentially "cornered" into trying to route the power line through a large conservation easement, called the Connecticut Lakes Headwaters. The governor at that time, Democrat Maggie Hassan, said she opposed such a move on the part of Northern Pass.Second Time Around: Northern Pass Announces Alternative RouteIn June of 2013, Northern Pass unveiled its second proposed route. Abandoning its previous strategy (and $40 million in land purchases) altogether, the project proposed building along existing state and local North Country roadways in Clarksville and Stewartstown. In a nod to project opponents, Northern Pass also said it will bury 7.5 miles of line in Stewartstown, Clarksville, and under the Connecticut River. That raised the price tag on the project from $1.2 billion as initially proposed to about $1.4 billion. While opponents said this move was progress, many – including the Forest Society – maintained that Northern Pass should be able to bury all 180 miles of power lines.Final Route: Burial through the White Mountains0000017a-15d9-d736-a57f-17ff8a620000 After years of continued opposition, Northern Pass made its final concession to critics. It downsized the powerline from an initial proposal of 1,200 megawatts to 1,090 to take advantage of a new technology, known as HVDC lite. This move made it more economical to bury portions of the line, and Eversource said it was now willing to bury 52 additional miles of the project. The new route would be alongside state roadways as the project passed through the White Mountain National Forest.While the governor called the change “an important improvement,” she also said “further improvements” to the project should be made. The partial burial did not placate the project’s fiercest opponents, but some speculated that it would help the project clear one significant hurdle: whether it would get approval to use public lands from the top official at the White Mountain National Forest. The move pushed the estimated price tag up again, to $1.6 billion, now for a project that would deliver less power.With its new route in hand, project officials filed to build the project in October of 2015.Before the Site Evaluation CommitteeThe application to state officials was likely the longest and most complicated in the state’s history, and 161 individuals, interest groups, and municipalities asked to be allowed to participate in the process to evaluate the merits of the project.Given the size and complexity of the project, many of the interveners pushed for a longer review than the standard one year that state law dictates. In May of 2016, those groups got their wish, and the decision was pushed back 9 months. The final deadline was set for September of 2017. However, once the proceeding got under way, it was clear that even this delay would not allow time to hear from all of the witnesses called by the various interveners. Early in September of 2017 it was delayed again, with a final decision set for February 2018.DeniedOn February 1st, 2018, the New Hampshire Site Evaluation Committee voted unanimously to deny the permit for Northern Pass, a decision that triggered an appeals process that was taken up by the New Hampshire Supreme Court in late 2018.In May of 2019, the court heard orgal arguments on the appeal.On July 19, 2019, the court issued its ruling. In a unanimous decision, the SEC's rejection of the project was upheld, likely marking the end of Northern Pass as it was proposed.

Northern Pass Says It Will Look for A Different Route in the North Country

Faced with strong, statewide opposition officials from Northern Pass say they are reworking parts of their plan, including finding a better route through the North Country. NHPR’s Chris Jensen reports.

NorthernPass officials say they want to change some important parts of their plan to bring 1,200 megawatts of hydro-electric power from Canada.

 Their possible changes include finding a new route between Canada and Groveton, one that will calm the furor in the North Country.

 Last month at least 2,300 people attended seven public hearings on the project.

 And except for a few who spoke about the employment possibilities, most of those who attended expressed strong opposition.

 Senator Kelly Ayotte and Rep. Charles Bass have also come out against the project while Sen. Jeanne Shaheen has expressed concern.

 “Northern Pass is clearly feeling the ground moving beneath them on this project.”

 That’s Christophe Courchesne.

 He is a lawyer with the Conservation Law Foundation, which is opposing the project.

 Indeed Northern Pass admits the opposition made it re-consider.

 Martin Murray is a spokesman for Public Service of New Hampshire which is involved in the project.

 “We understand our current proposal is not acceptable.”

 In a new filing with the Department of Energy Northern Pass asked for 60 days to try and find a new route north of Groveton.

 PSNH’s Martin Murray:

  “Well, we’re optimistic that in the North Country we will be able to determine a route that does have the support of landowners and of the local communities and minimizes any impact.”

 But Murray says that will still require cutting a new right of way.

 Northern Pass also wants to withdraw the five alternate routes included in the original plan.

 From a political, practical standpoint that could reduce opposition from people who are no longer concerned it could end up in their backyard.

 What isn’t changing is the route south of Groveton.

 It would follow the existing right of way.

 That would include passing Littleton and crossing the White Mountain National Forest onto to Franklin and eventually Deerfield.

 Northern Pass says building that line would provide about 1,200 construction jobs over three years.

 In the most recent filing Northern Pass also addressed three alternatives raised by critics.

 One was why the lines can’t be laid in the Connecticut River?

 Northern Pass basically said the river is too shallow for the equipment needed to lay the cable.

 Another is why the lines can’t be buried?

 Northern Pass said that requires heavy equipment that would impractical to move into the area and it would cost too much.

 The third is why the power can’t be paired up with a project from Canada that runs through New York State.

 Northern Pass said that would send power into New York instead of New Hampshire and New England.

 The Conservation Law Foundation’s Courchesne says the Northern Pass request is a mixed bag.

 “Northern Pass seems to be digging in its heels and dismissing some of the alternatives that we think need to be considered very carefully.”

 That includes the alternatives such as burying the power lines.

 “On the other hand the filing also says they are taking a step back and looking for alternative routes in the North Country and they want more time to do that.”

 The Northern Pass request to the DOE is unusual.

 Typically utilities don’t ask to modify a plan after it has been submitted and public hearings have been held.

 It is not clear how long it could take for the agency to act.

Related Content

You make NHPR possible.

NHPR is nonprofit and independent. We rely on readers like you to support the local, national, and international coverage on this website. Your support makes this news available to everyone.

Give today. A monthly donation of $5 makes a real difference.